* Progress:
 
* Progress:
** HV supply installed, with remote operation-completed
+
**  
** Macro pulsing wiring- completed
+
** Fiber-optic communications wired and functioning- completed
+
** Gun installed with Josh's spool- completed
+
** Hot deck constructed and installed -completed
+
** RF transmission line constructed and installed- completed
+
** Troubleshooting DC voltages on hot deck- completed
+
** Gun under vacuum removal turbo- completed
+
  
  
 
* Remaining Tasks:
 
* Remaining Tasks:
** Cathode activation- waiting on Karl's instruction
+
**  
** HV processing- needs to be after cathode activation
+
** RF/macro pulsing troubleshooting- need scope and power meter
+
** Survey and alignment- need to scheduled
+
** Hot Deck OSP
+
** Fiber-plastic corona cover
+
  
  
 
* Schedule:
 
* Schedule:
** RF troubleshooting as soon as I have required equipment. Start today?
+
**
** Cathode activation- as soon as I get the required settings from Karl it will be completed the same day.
+
** HV processing (with cover and RadMon)- the day after cathode activation.
+
** survey and alignment- ideally Friday 7/19/19
+