GTS meeting 7 29 19

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
  • Survey:
media:DT_F1933.pdf
Drawing: media:TGun_Cathode_drawing.pdf
  • Overview:
    • HV Processing needs to be done
    • Survey and alignment was completed. Final placement of solenoid needs to be set
    • SMA cable causing RF issue has been replaced and final RF work needs to be done
    • DC Bias Supply is in John Musson's Lab being modified and tested: working schedule unknown
    • open valve to beam-line and produce initial beam
    • determine cut-off voltages with solenoid on/off
    • produce RF bunched beam of specific bunch charges
    • measure bunch properties of magnetized and non-magnetized beam
    • produce 65 mA magnetized beam as part of Xelera deliverables


  • 7/29 work plan:
    • complete gun enclosure for corona mitigating nitrogen flow
    • Install radiation monitors
    • modify Hot deck HV contact
    • finalize Solenoid placement
    • connect the anode bias
  • 7/30 work plan:
    • set up camera to visually monitor HV (waiting on updated software)
    • Standard HV processing
    • HV processing with solenoid on if standard HVP goes well
  • 7/31 work plan:
    • Finish RF work, Final check of SCAM and create supply to voltage chart
    • Check DC Bias Supply progress (possibly reinstall)
  • 8/1-onward work plan:
    • Depends on what happens up to this date...