  • Update:
    • HVPS cable wasn't grounded. It is now, but PSS Still trips.
    • Issues performing sweep due to PSS configuration error
    • Cathode grid possibly gone. Need to replace cathode
    • Two dead pico-amp meters, flow meters are not working. Note: All of these items and computer for HVPS Software are on same fuse box.
  • Talking Points:
    • Cathode/Grid Issues, risks and risk mitigation
    • HV Processing (cathode hot/cold, Krypton)
    • Mini-flange leak valve?
    • larger Ion pump?
    • extra shielding on HV Cable or move supply again?
    • Change power source (fuse box) for racks?