Difference between revisions of "GTS meeting 9 11 17"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "* High current runs * Shutdown Plan: ## Install new YAG screen at viewer 3 ## Fix existing harp and install 20 µm tungsten wire ## Add a new CEBAF-style harp with 10 µm t...")
 
Line 4: Line 4:
 
* Shutdown Plan:
 
* Shutdown Plan:
  
## Install new YAG screen at viewer 3
+
# Install new YAG screen at viewer 3
## Fix existing harp and install 20 µm tungsten wire
+
# Fix existing harp and install 20 µm tungsten wire
## Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps)
+
# Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps)
## Replace leaky vent valve
+
# Replace leaky vent valve
## Replace bad ion pump
+
# Replace bad ion pump
  
  
 
* Next Shutdown – December 2017:
 
* Next Shutdown – December 2017:
## Install TE011 cavity
+
# Install TE011 cavity

Revision as of 08:01, 11 September 2017

  • High current runs


  • Shutdown Plan:
  1. Install new YAG screen at viewer 3
  2. Fix existing harp and install 20 µm tungsten wire
  3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
  4. Replace leaky vent valve
  5. Replace bad ion pump


  • Next Shutdown – December 2017:
  1. Install TE011 cavity