(this page was updated November 7, 2019)
Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations:
Run# | 0 | 1 | 2 | 3 | 4 | 5 |
Objective | IBC installation | Booster Commissioning | Aperture target/Empty Target | Unpolarized Target | Polarized Target | Polarized Target |
Tiles OFF and ON sequence | OFF/ON | not required | OFF/ON | OFF/ON/OFF/ON | OFF/ON/OFF/ON/OFF/ON | OFF/ON/OFF/ON/OFF/ON |
# times Neil visits the rooftop | 2 (done) | 0 | 2 | 4 | 6 | 6 |