(this page was updated November 7, 2019)
 +
 
Andy's proposed run plan, the hard part is scheduling this work before May 2020.  And lots of rooftop manipulations:
 
Andy's proposed run plan, the hard part is scheduling this work before May 2020.  And lots of rooftop manipulations:
  
 
{| class="wikitable" style="text-align: center; color: green;"
 
{| class="wikitable" style="text-align: center; color: green;"
 
|Run#
 
|Run#
 +
|X
 
|0
 
|0
 
|1
 
|1
Line 8: Line 11:
 
|3
 
|3
 
|4
 
|4
|5
 
 
|-
 
|-
 
|Objective
 
|Objective
Line 20: Line 22:
 
|Tiles OFF and ON sequence
 
|Tiles OFF and ON sequence
 
|OFF/ON  
 
|OFF/ON  
|-
+
|not required
 
|OFF/ON
 
|OFF/ON
 
|OFF/ON/OFF/ON
 
|OFF/ON/OFF/ON

Latest revision as of 15:19, 7 November 2019

(this page was updated November 7, 2019)

Andy's proposed run plan, the hard part is scheduling this work before May 2020. And lots of rooftop manipulations:

Run# X 0 1 2 3 4
Objective IBC installation Booster Commissioning Aperture target/Empty Target Unpolarized Target Polarized Target Polarized Target
Tiles OFF and ON sequence OFF/ON not required OFF/ON OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON OFF/ON/OFF/ON/OFF/ON
# times Neil visits the rooftop 2 (done) 0 2 4 6 6