Difference between revisions of "January 13, 2020 - Service providers"

From Ciswikidb
Jump to navigation Jump to search
Line 4: Line 4:
 
* Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
 
* Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
 
* During the 2020 SAD we will...
 
* During the 2020 SAD we will...
:-Make the gun operate a 200 kV
+
:-Make the gun operate a 200 kV (A: make present gun operate 200 kV, B: install new electrode)
 
:-Reconfigure beam line extending from gun through chopper
 
:-Reconfigure beam line extending from gun through chopper
 
:-Commission the new gun and beam line with 200 keV beam
 
:-Commission the new gun and beam line with 200 keV beam
Line 12: Line 12:
 
:-This means the capture and QCM remain until Booster installed
 
:-This means the capture and QCM remain until Booster installed
 
:-This also means we'll operate the gun and beam line at 130 keV until that time too
 
:-This also means we'll operate the gun and beam line at 130 keV until that time too
 +
 +
===Status of the 2020 beam line upgrade===
 +
* Layout
 +
:-We have a preliminary ME layout, mainly to tally that everything will fit; notably we have a pretty good idea what everything will be
 +
:-CIS/INJ/CASA are evaluating exact sequence for functionality and to model the envelope, aiming to have this pretty well defined in Feb
 +
* On the topic of everything, how does this go:
 +
:Magnets
 +
::-Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround
 +
::-Wien filters, PO written, coils due early march
 +
::-15 deg dipole, bids received, anticipate PO within a ~week
 +
::-steering coils, should have enough in hand, will order spares once layout done
 +
::-Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially

Revision as of 10:36, 13 January 2020

Service providers discussion

Scope of 2020 SAD

  • Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
  • During the 2020 SAD we will...
-Make the gun operate a 200 kV (A: make present gun operate 200 kV, B: install new electrode)
-Reconfigure beam line extending from gun through chopper
-Commission the new gun and beam line with 200 keV beam

Beyond 2020 SAD

  • We will not modify the configuration downstream of chopper until new Booster goes in
-This means the capture and QCM remain until Booster installed
-This also means we'll operate the gun and beam line at 130 keV until that time too

Status of the 2020 beam line upgrade

  • Layout
-We have a preliminary ME layout, mainly to tally that everything will fit; notably we have a pretty good idea what everything will be
-CIS/INJ/CASA are evaluating exact sequence for functionality and to model the envelope, aiming to have this pretty well defined in Feb
  • On the topic of everything, how does this go:
Magnets
-Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround
-Wien filters, PO written, coils due early march
-15 deg dipole, bids received, anticipate PO within a ~week
-steering coils, should have enough in hand, will order spares once layout done
-Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially