January 13, 2020 - Service providers

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Service providers discussion

Structure of these meetings

  • Focus on resource issues, status, schedule, logistics, staying on same page
  • Every two weeks for now
  • I will create a mass mailing list to communicate

Scope of 2020 SAD

  • Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
  • During the 2020 SAD we will...
-Make the gun operate at 200 kV (A: make present gun operate 200 kV, B: install new electrode)
-Reconfigure beam line extending from gun up to chopper (stretch goal is replace chopping chamber itself)
-Commission the gun + beam line with 200 keV beam

Beyond 2020 SAD

  • We will not modify the configuration downstream of chopper until new Booster goes in
-This means the capture and QCM remain until Booster installed
-This also means we'll operate the gun and beam line at 130 keV until that time too

Status of the 2020 beam line upgrade

  • Layout
-We have a preliminary ME layout, w/ sequence and approximate tally of elements
-CIS/INJ/CASA are simulating and evaluating layout for functionality and performance now
-Goal is to finalize ME layout and the before v. after by late Feb, give or take
  • Vacuum
-Valves, same number, maybe one less
-IPs, Marcy has as-is tally, should be OK, may need to order couple small pumps
-DP stations, new NEG's for Y- and DP chamber, otherwise the same
  • Magnets
-Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround
-Wien filters, PO written, coils due early march
-Still need two 20A PS installed
-Still need WIen filter HV PS, switches, cables installed
-15 deg dipole, bids received, anticipate PO within a ~week (more S&A work than usual)
-1 trims now w/ comparator, need the same
-Haimons-style steering coils, should have enough in hand, will order spares once layout done
-Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially
-6 trims now, probably need less
  • Diagnostics
-Harp, have two now, aiming for one later
-Viewers, repair cracked YAG; tally is similar to what we have now, final TBD
-Brock cavity, goes away
-Current monitors, keep A1/A2/PCUP
-BPM's, TBD, but similar number
-Magic beam locating device, none
  • RF
-prebuncher, probably the same, but need more power >30W?...TBD
-choppers, leave as-is and decided to retain the captured solenoids (so no vacuum work or removal)
  • Chopping chamber
Designing entirely new 1:1 replacement, not sure it will be ready this SAD, but that's the goal, stay tuned

Timeline

  • HV Condition Gun2 (1 week)
(X shifts) Tee to 200 kV
  • Gun/NEG tube vacuum work (2-3 weeks)
(10 day) Small shed bake
(X day) HV condition small shed @ 200 kV
(3 day) Replace NEG tube + anode flange
  • Rebuild beam line (7-8 weeks)
(2 days) Make everything safe
(3 days) Disconnects of cables and controls and dumping of penetrations
(2 days) Girder vacuum disconnects and removal to labs and tunnel storing
(2-3 weeks) Wien breakdown + shop work + re-assembly + HV testing + mapping)
(2-3 weeks) Populating new girder layouts with existing hardware + alignments
(3 days) Pedestal modifications
(1 week) Installation, 1A, vacuum hookups, 2A
(2 weeks) Bakeouts
(1 week) Cable reconnects and HCO
  • Beam Commissioning Jobs (2-3 weeks)
(9 shift) HCO w/ beam first time
(2 shift) Injector steering script for new location of correctors and bpm’s
(4 shift) Wien filter spin calibration w/ Mott (at 130 keV)
(4 shift) Wien optics measurements and quadrupole correction
(2 shift) Dipole optics measurement to finalize shims
(2 shift) Develping a matching criteria
(1 shift) PSS kicker @ 130 keV and 200 keV
(9 shift) Gun lifetime checkout