* Important CEBAF Dates and Preliminary Commissioning Plan (PCP) [[media:210125_CommissioningPlan.docx]]
 
* Important CEBAF Dates and Preliminary Commissioning Plan (PCP) [[media:210125_CommissioningPlan.docx]]
 
* Schedule updated 1/25, included Preliminary Commissioning Plan SAD July 2, 2021 [[media:210125_AIPINJ_Schedule.xlsx]]
 
* Schedule updated 1/25, included Preliminary Commissioning Plan SAD July 2, 2021 [[media:210125_AIPINJ_Schedule.xlsx]]
* [[File:210125_SchedulePic.jpg|thumb|center|300px|alt=210125_SchedulePic.]]
+
* [[File:210125_SchedulePic.jpg|thumb|center|600px|alt=210125_SchedulePic.]]
  
 
; Carlos (5 min) - Gun performance and 200 kV conditioning plans
 
; Carlos (5 min) - Gun performance and 200 kV conditioning plans

Revision as of 13:42, 25 January 2021

Meeting Info =

Monday's from 1-2 pm via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/140278851
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 140278851#
Passcode : 2864   (anybody can then start the meeting)

Meeting January 25, 2021

Joe (5 min) - Phase 1 schedule status, plan for HCO, and PSS readiness
Carlos (5 min) - Gun performance and 200 kV conditioning plans
Shukui (5 min) - Laser status and startup plans
Riad (5 min) - Wien controls and spin rotator calibration plans
media:Spin_Rotator_Calibration_plans.pdf
Marcy (5 min) - Vacuum beam line status (viewers, apertures, pumping) and post-bake HCO plans
Reza, Alica, Marcy, Yan, Dennis (30 min) - Beam commissioning plans
Daniel, Eric (5 min) - Toolbox, ENG/software coordination, scheduling shifts, screen updates
media:AIPINJ-PhaseI-BeamDrivers_1.25.21.pdf