January 27, 2020 - Resource Meeting

From Ciswikidb
Revision as of 12:42, 23 January 2020 by Grames (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Announcements

  • Injector upgrade calendar
Run (now - May 6)
Phase 1 (May 6 - end of 2020)
Run (Jan 2021 - Sep 13 2021)
Phase 2 (Sep 13 - end of 2021)
  • Mailing list => aipinj@jlab.org
  • ME group effort growing (Danny Machie, Shaun Gregory, Jeff Hoerger)

Many good things happening, down the beam line...

  • New 200kV small shed cathode electrode at machine shop (like electron at UITF)
  • New gun 10" anode flange being designed to locate a steering coil closer to the gun
  • Phil/Marcy starting to NEG coat vacuum chambers; need a 1kW sputtering PS that works (1 kV, 1 mA)
  • PO for 200 kV injector solenoids written (delivery April - June)
  • Shaun designed alignment fixture for new beam line solenoids
  • PO for 200 kV Wien magnet coils written (delivery March)
  • PO to be written for new 15 deg dipole next week
  • Chase assigning new names for dipole and solenoids
  • Starting to study which laser vacuum window to use 2-3/4" as-is, or 4-1/2"
  • Curt waiting on kV spec for prebuncher @ 200 kV, for Watt in S.S. cavity
  • Reza/Alicia/Dennis evaluating re-ordering of layout
  • Looking at installing valve downstream of chopper #2 this down
  • Gary Cheng inquiring about checking cryo lines between QCM and Booster
  • 5D beam line will be removed
  • Neil/Anthony working plan to build table to move QCM/Booster


ATLIS Tasks

Quick links