Difference between revisions of "July 11,, 2019 - Weekly AIPINJ Meeting"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "=== Agenda === ;Schedule *Whiteboard pic media:190711_down.jpg *Commissioning plan ;Layout/Tasks ;Simulations")
 
 
(6 intermediate revisions by the same user not shown)
Line 3: Line 3:
 
;Schedule
 
;Schedule
 
*Whiteboard pic [[media:190711_down.jpg]]
 
*Whiteboard pic [[media:190711_down.jpg]]
*Commissioning plan
+
*Suggests installation & commissioning plan like this:
 +
:May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
 +
:Nov ~ Booster/QCM swap between CEBAF/UITF
 +
:Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing
 +
:Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
  
 
;Layout/Tasks
 
;Layout/Tasks
 +
[[media:190711_punchlist.docx]]
  
 
;Simulations
 
;Simulations
 +
* elegant layout gun to QCM by ~ end of July
 +
* gpt ~ goals are?

Latest revision as of 09:53, 11 July 2019

Agenda

Schedule
May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
Layout/Tasks

media:190711_punchlist.docx

Simulations
  • elegant layout gun to QCM by ~ end of July
  • gpt ~ goals are?