Difference between revisions of "July 11,, 2019 - Weekly AIPINJ Meeting"

From Ciswikidb
Jump to navigation Jump to search
Line 14: Line 14:
  
 
;Simulations
 
;Simulations
 +
* elegant layout gun to QCM by ~ end of July
 +
* gpt ~ goals are?

Revision as of 09:51, 11 July 2019

Agenda

Schedule
May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF
Feb ~ Cool Booster at CEBAF, SRF commission
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
Layout/Tasks

media:190711_punchlist.docx

Simulations
  • elegant layout gun to QCM by ~ end of July
  • gpt ~ goals are?