*Suggests and installation commissioning plan like this:
 
*Suggests and installation commissioning plan like this:
:May-Oct ~ 6 months to rebuild the 200keV beam line
+
:May-Oct ~ 6 months to rebuild the 200keV beam line up to QCM
 
:Nov ~ Booster/QCM swap between CEBAF/UITF
 
:Nov ~ Booster/QCM swap between CEBAF/UITF
 
:Dec-Jan ~ Install and instrument Booster at CEBAF
 
:Dec-Jan ~ Install and instrument Booster at CEBAF

Revision as of 09:49, 11 July 2019

Agenda

Schedule
May-Oct ~ 6 months to rebuild the 200keV beam line up to QCM
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF
Feb ~ Cool Booster at CEBAF, SRF commission
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?