;Schedule | ;Schedule | ||
*Whiteboard pic [[media:190711_down.jpg]] | *Whiteboard pic [[media:190711_down.jpg]] | ||
− | *Suggests | + | *Suggests installation & commissioning plan like this: |
:May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM) | :May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM) | ||
:Nov ~ Booster/QCM swap between CEBAF/UITF | :Nov ~ Booster/QCM swap between CEBAF/UITF | ||
Line 11: | Line 11: | ||
;Layout/Tasks | ;Layout/Tasks | ||
+ | [[media:190711_punchlist.docx]] | ||
;Simulations | ;Simulations |
Revision as of 09:50, 11 July 2019
Agenda
- Schedule
- Whiteboard pic media:190711_down.jpg
- Suggests installation & commissioning plan like this:
- May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
- Nov ~ Booster/QCM swap between CEBAF/UITF
- Dec-Jan ~ Install and instrument Booster at CEBAF
- Feb ~ Cool Booster at CEBAF, SRF commission
- Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
- Layout/Tasks
- Simulations