Agenda

Schedule
May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF
Feb ~ Cool Booster at CEBAF, SRF commission
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
Layout/Tasks

media:190711_punchlist.docx