Agenda

Schedule
May-Sep ~ 5 months to rebuild the 200keV beam line
Oct-Dec ~ move Booster to CEBAF, install, ready to cool by Christmas
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF
Feb ~ Cool Booster at CEBAF, SRF commission
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
Layout/Tasks
Simulations