Agenda

Schedule
May-Oct ~ 6 months to rebuild the 200keV beam line (gun, chopper, up to QCM)
Nov ~ Booster/QCM swap between CEBAF/UITF
Dec-Jan ~ Install and instrument Booster at CEBAF, cool and SRF testing
Feb-Mar ~ Commissiong 10 MeV beam to FC2, ILD?
Layout/Tasks

media:190711_punchlist.docx

Simulations
  • elegant layout gun to QCM by ~ end of July
  • gpt ~ goals are?