Difference between revisions of "July 19, 2022 - Group meeting"

From Ciswikidb
Jump to navigation Jump to search
(5 intermediate revisions by the same user not shown)
Line 5: Line 5:
 
* Procurement's deadline for FY22 purchases is 8/19, anything later is not guaranteed
 
* Procurement's deadline for FY22 purchases is 8/19, anything later is not guaranteed
 
* Crystal is taking a new job in procurement, beginning 8/1
 
* Crystal is taking a new job in procurement, beginning 8/1
 +
** CIS web page
 
* Nate is now our point of contact for I&C jobs
 
* Nate is now our point of contact for I&C jobs
* CIS web page
+
* Job postings
 +
* Early scientist lunchtime gatherings
 +
* Cleaning up 1137, UITF shop, making space for students and phase 2 ugprade
  
; Papers and reports
+
; UITF (this week and next week)
* Early scientist lunchtime gatherings
+
* Understanding why polarization is zero?  https://logbooks.jlab.org/entry/4017011
* Valeria's - summer study report
+
* Test laser for kicker in Aug?, order a spare amplifier, when is 1497 needed?
* Matt's PV - graphics from Joe Wien, Riad PV
 
* Sajini's and Mamun's and Riad's magnetized beams - peer review
 
* Josh's and Joe's biased anode - author review
 
  
 
; CEBAF
 
; CEBAF
 
* Hall D TMG failed last week, was a cold solder joint, it was repaired and in 1137 locker w/ shutter
 
* Hall D TMG failed last week, was a cold solder joint, it was repaired and in 1137 locker w/ shutter
 
* Nate reported they are now able to successfully load firmware to seed laser board, ready for testing soon
 
* Nate reported they are now able to successfully load firmware to seed laser board, ready for testing soon
* Thia is reporting at this week's S&T review that KL will begin installation in 2025, for operating in 2026-2028, let's add PR to FY23 budget request (need full scope integration w/ RF, software, etc.
+
* KL will begin installation in 2025, for operating in 2026-2028, let's add PR to FY23 budget request (need full scope integration w/ RF, software, etc.?
* A2/IYG0I02 charging
+
* A2/IYG0I02 charging https://logbooks.jlab.org/entry/4015377
* Injector bpm's respond to current differently
+
* Injector bpm's respond to current differently https://logbooks.jlab.org/entry/4014457
 
* Gun2 lifetime
 
* Gun2 lifetime
  
; UITF (this week and next week)
+
; Your Projects
* Yan wants to recheck some booster measurements.  deflection, rotation, 2-cell GSet calibration
 
* Max wants to repeat the measurement of spectral content on beam, for beam to the MeV spectrometer, in CW (I will ask David H. for permission, someone from RadCon will need to be there during data taking)
 
* Gigi wants beam
 
* Tomasz and Rama want time for LLRF3.0 development
 
* Joe/Riad/Valeria want some time to finish Mott, what amounts to ~finish Mott checkout + ~ 1 shift for tgt. thick & spin dance
 
  
; Your Projects
+
; Papers and reports
* Gabriel 500 kV insulator
+
* Valeria's - summer study report
* Marcy mini-Mott
+
* Matt's PV - graphics from Joe Wien,  Riad PV
* Mamun TE011 cavity & vacuum work
+
* Sajini's and Mamun's and Riad's magnetized beams - out for peer review
* Riad LDRD
+
* Josh's and Joe's biased anode - author review

Revision as of 21:21, 18 July 2022

July 19

General business
  • NA-PAC proceedings are due 8/2, its polite to submit for internal review a ~week ahead NA-PAC
  • Procurement's deadline for FY22 purchases is 8/19, anything later is not guaranteed
  • Crystal is taking a new job in procurement, beginning 8/1
    • CIS web page
  • Nate is now our point of contact for I&C jobs
  • Job postings
  • Early scientist lunchtime gatherings
  • Cleaning up 1137, UITF shop, making space for students and phase 2 ugprade
UITF (this week and next week)
CEBAF
  • Hall D TMG failed last week, was a cold solder joint, it was repaired and in 1137 locker w/ shutter
  • Nate reported they are now able to successfully load firmware to seed laser board, ready for testing soon
  • KL will begin installation in 2025, for operating in 2026-2028, let's add PR to FY23 budget request (need full scope integration w/ RF, software, etc.?
  • A2/IYG0I02 charging https://logbooks.jlab.org/entry/4015377
  • Injector bpm's respond to current differently https://logbooks.jlab.org/entry/4014457
  • Gun2 lifetime
Your Projects
Papers and reports
  • Valeria's - summer study report
  • Matt's PV - graphics from Joe Wien, Riad PV
  • Sajini's and Mamun's and Riad's magnetized beams - out for peer review
  • Josh's and Joe's biased anode - author review