June 5, 2019

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

We'll meet in TL-2561a on June 5, 2019 @ 9:30am.

Unusual Circumstances

There have been 3 recent incidents where fire trucks responded to alarms on the accelerator site:

  1. May 21, 2019 - 10A card in a 1A slot resulting in a burned up air core magnet at 0L09 - https://logbooks.jlab.org/entry/3683097
  2. May 30, 2019 - Mis-wired 25A short on 100A shunt resulting in burned insulation on a ZA magnet - https://logbooks.jlab.org/entry/3684466
  3. May 31, 2019 - Failed transformer winding on 28 year old klystron cathode power supply - https://logbooks.jlab.org/entry/3684618

In our realm of the accelerator, have we had enough resources and time to reasonably assess our systems and have confidence for high reliability this summer?

The next 7 months!

CEBAF
LERF
  • Cryo has headroom to support LCLS/SRF operations this summer
  • Status of gain switch fiber oscillator at LERF
  • Forecast for commissioning and radio-isotope run
UITF
  • ARR, summer beam program, and the next gun electrode
GTS
  • TGun schedule and outlook for the rest of the year