June 8, 2016 - Monthly 4-laser Upgrade Status Meeting

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

We will have the next 4-laser monthly meeting on Wednesday, June 8 @ 11am EST in TL-1227.

Wiki link here: https://wiki.jlab.org/ciswiki/index.php/June_8,_2016_-_Monthly_4-laser_Upgrade_Status_Meeting

Let's hear about following topics with people listed helping lead the discussion...

Joe - Long term 4-hall Ops

Joe - Short term Summer SAD

John - Laser readiness and plans

Mike - PC104 serial migration (laser amplifiers/TEC controllers)

Roger/Gary - SCAM status

Henry - PSS readiness and plans

Tomasz - LLRF readiness and plans

Commissioning

  • Communication to Amplifiers and TEC controllers
  • Collinearity of lasers to photocathode, Beam Modes, Polarization
  • SCAM testing + photodiode traces of beam modes
  • PSS certification of shutters + good aperture through shutters
  • Screens - Ops support
  • Pre-Beam HCO