; CEBAF
 
; CEBAF
 
* Restoration begins July 16 (~5 weeks)
 
* Restoration begins July 16 (~5 weeks)

Revision as of 08:12, 9 June 2021

Group business
CEBAF
  • Restoration begins July 16 (~5 weeks)
  • Commissioning - I don't see how it all fits, restoring CEBAF for the Fall run would be top priority
  • Things maybe left to do?
  1. PCup - water leak and pig-tail?
  2. Wien HV - work with injector group to decide mode of operation
  3. Harp - work with ME group to develop a solution, decide if/when to install
  • Phase 2 - who thinks we're ready by January?
UITF
  • Restoration begins July 26 (~6 weeks)
  • Clean HV chamber
  • New cathode and anode spider (~week?)
  • Prep chamber - mask, pucks, Sb source
  • Bake (~week) + condition (~week)
GTS
  • Re-building depo, gun, beam line, laser, HV controls - wow!
  • Once built, program til end of year...
Students, FOA's, LDRD's, SBIR's ...
  • Students - Sajini, Josh
  • LDRD's - Shukui, Joe
  • Photocathode & HV FOA's
  • SBIR's