From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
* new hires
 
* new hires
 
* MEDCON4
 
* MEDCON4
 +
# maximize tele-working
 +
# daily self certification remains
 +
# on-site in person meetings allowed
 +
# vaccination reporting encouraged
 +
#face masks required if unvaccinated
 
* re-"Grouping"
 
* re-"Grouping"
 +
* Matt...
 
* power outages (CEBAF, TL, UITF, GTS) - [[media:Building 58 After hour e-call listing June.08.2021 - PJD.docx]]
 
* power outages (CEBAF, TL, UITF, GTS) - [[media:Building 58 After hour e-call listing June.08.2021 - PJD.docx]]
 
* Geoff is inquiring if we want another stream of PhD students
 
* Geoff is inquiring if we want another stream of PhD students
Line 23: Line 29:
  
 
; UITF
 
; UITF
 +
* Mike McCaughn work coordinator/facility manager & Safety Warden
 
* Restoration begins July 26 (~6 weeks)
 
* Restoration begins July 26 (~6 weeks)
 
* Clean HV chamber
 
* Clean HV chamber

Latest revision as of 09:27, 9 June 2021

Group business
  • new hires
  • MEDCON4
  1. maximize tele-working
  2. daily self certification remains
  3. on-site in person meetings allowed
  4. vaccination reporting encouraged
  5. face masks required if unvaccinated
Status on on our contribution to Lab projects
  • EIC - expected, scope coordination ramping up, for FY22 (and maybe FY21 contribution)
  • ILC - solicited, work packages being developed, do we want to contribute? maybe we need to meet/discuss what exactly, resources, timeline
CEBAF
  • Restoration begins July 16 (~5 weeks)
  • Commissioning - I don't see how it all fits, restoring CEBAF for the Fall run would be top priority
  • Things maybe left to do?
  1. PCup - water leak and pig-tail?
  2. Wien HV - work with injector group to decide mode of operation
  3. Harp - work with ME group to develop a solution, decide if/when to install
  4. Mode-locked fiber laser
  5. Mott target ladder swap
  • Phase 2 - who thinks we're ready by January?
UITF
  • Mike McCaughn work coordinator/facility manager & Safety Warden
  • Restoration begins July 26 (~6 weeks)
  • Clean HV chamber
  • New cathode and anode spider (~week?)
  • Prep chamber - mask, pucks, Sb source
  • Bake (~week) + condition (~week)
GTS
  • Re-building depo, gun, beam line, laser, HV controls - wow!
  • Once built, program til end of year...
LERF
  • Per Camille, pause on LERF upgrades
  • Presently, don't anticipate radio-isotope runs for a ~year-ish?
  • I am suggesting we move to the LERF, offices, labs, injector, etc....what do you think of this?
Students, FOA's, LDRD's, SBIR's ...
  • Students - Sajini, Josh
  • LDRD's - Shukui, Joe
  • Photocathode & HV FOA's
  • SBIR's