Difference between revisions of "June 9, 2021 - Group Meeting"
Jump to navigation
Jump to search
Line 12: | Line 12: | ||
# Harp - work with ME group to develop a solution, decide if/when to install | # Harp - work with ME group to develop a solution, decide if/when to install | ||
* Phase 2 - who thinks we're ready by January? | * Phase 2 - who thinks we're ready by January? | ||
− | < | + | <p> |
; UITF | ; UITF | ||
* Restoration begins July 26 (~6 weeks) | * Restoration begins July 26 (~6 weeks) | ||
Line 19: | Line 19: | ||
* Prep chamber - mask, pucks, Sb source | * Prep chamber - mask, pucks, Sb source | ||
* Bake (~week) + condition (~week) | * Bake (~week) + condition (~week) | ||
− | < | + | <p> |
; GTS | ; GTS | ||
* Re-building depo, gun, beam line, laser, HV controls - wow! | * Re-building depo, gun, beam line, laser, HV controls - wow! | ||
* Once built, program til end of year... | * Once built, program til end of year... | ||
− | < | + | <p> |
; Students, FOA's, LDRD's, SBIR's ... | ; Students, FOA's, LDRD's, SBIR's ... | ||
* Students - Sajini, Josh | * Students - Sajini, Josh |
Revision as of 08:07, 9 June 2021
- Group business
- new hires
- MEDCON4
- re-"grouping"
- CEBAF
- Restoration begins July 16 (~5 weeks)
- Commissioning - I don't see how it all fits, restoring CEBAF for the Fall run would be top priority
- Things maybe left to do?
- PCup - water leak and pig-tail?
- Wien HV - work with injector group to decide mode of operation
- Harp - work with ME group to develop a solution, decide if/when to install
- Phase 2 - who thinks we're ready by January?
- UITF
- Restoration begins July 26 (~6 weeks)
- Clean HV chamber
- New cathode and anode spider (~week?)
- Prep chamber - mask, pucks, Sb source
- Bake (~week) + condition (~week)
- GTS
- Re-building depo, gun, beam line, laser, HV controls - wow!
- Once built, program til end of year...
- Students, FOA's, LDRD's, SBIR's ...
- Students - Sajini, Josh
- LDRD's - Shukui, Joe
- Photocathode FOA's
- SBIR's