Difference between revisions of "MOLLER PQB Meeting December 6, 2023"

From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by the same user not shown)
Line 9: Line 9:
 
1- Update firmware of helicity generator board to have MOLLER settings on December 20th, 2023
 
1- Update firmware of helicity generator board to have MOLLER settings on December 20th, 2023
  
2- Next MOLLER tests are in January 2024. For next beam studies 12/13/2023: 0700-1200 to Hall C
+
2- Next MOLLER beam tests are in January 2024. For next beam studies on 12/13/2023: 0700-1200 to Hall C
 
* FFB in Hall C
 
* FFB in Hall C
* Nathan (for an hour or so) : SEE BPM With Stripline Can Response Test
+
* SEE BPM With Stripline Can Response Test (cancelled due to FE contamination, to find a better location)
  
 
3- BCM Receiver tests update
 
3- BCM Receiver tests update
Line 17: Line 17:
 
4- RTP bench setup in TL 1137
 
4- RTP bench setup in TL 1137
  
5- Next week: Mike Tiefenback will present CEBAF energy management relevant for MOLLER
+
5- Next week: Mike Tiefenback will present CEBAF energy management relevant to MOLLER

Latest revision as of 11:08, 12 December 2023

In person in MCC Conference Room and with Zoom.

https://wiki.jlab.org/ciswiki/index.php/Parity_Quality_Beam

--

Agenda:

1- Update firmware of helicity generator board to have MOLLER settings on December 20th, 2023

2- Next MOLLER beam tests are in January 2024. For next beam studies on 12/13/2023: 0700-1200 to Hall C

  • FFB in Hall C
  • SEE BPM With Stripline Can Response Test (cancelled due to FE contamination, to find a better location)

3- BCM Receiver tests update

4- RTP bench setup in TL 1137

5- Next week: Mike Tiefenback will present CEBAF energy management relevant to MOLLER