= Meeting Info ==
 
= Meeting Info ==
We will meet Monday March 1 following Steve's 1:30 pm <u>'''via BlueJeans'''</u>:
+
We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion.  https://bluejeans.com/569476853
 
 
We will gather Monday at 1330 to continue the SAD discussion.  https://bluejeans.com/569476853
 
  
 
== Agenda ==
 
== Agenda ==
Line 8: Line 6:
 
; Installation status
 
; Installation status
 
* Schedule
 
* Schedule
**Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''')
+
**Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''') - maybe 1 or 2 weeks earlier
**We may be ready early by 1 or 2 weeks (no sooner than mid-March)
+
**'''4 weeks (Apr 5 - Apr 30)''' are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
**Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
 
**Goal is HCO/System readiness for everything up to FC#2
 
  
*Preliminary Songsheet
+
*Beam line layout
** Most recent posted on '''Friday Feb 23'''
+
** Preliminary ME songsheet released, up to date as of '''Feb 23''' on the upgrade home page => [[CEBAF Injector Upgrade]]
** Search Layout area on the upgrade home page => [[CEBAF Injector Upgrade]]
+
** 3D CAD model exists if you want to see something not there now
 +
** Cables: Like before trays (above & on girder) + 3 cable bundle drops (near Y, Laser, Chopper)
  
 
; DC/Magnet Jobs
 
; DC/Magnet Jobs
* What to expect in tunnel?
+
* Spreadsheet with magnet information updated as of '''Mar 1''' [[media:210301_Phase1_Magnet_Summary.xlsx]]
** Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
 
** There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
 
** Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable trays (above & on girder) + 3 cable bundle drops (Y, Laser, Chopper)
 
  
 
; Software Jobs
 
; Software Jobs
Line 30: Line 24:
  
 
; Other magnet jobs
 
; Other magnet jobs
*(JM) Complete magnet table I circulated
+
* '''Done''' (JM) Complete magnet table I circulated
 
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
 
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
 
*(RS/GC) FG solenoid special hysteresis for Gary
 
*(RS/GC) FG solenoid special hysteresis for Gary

Latest revision as of 14:53, 1 March 2021

Meeting Info =

We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion. https://bluejeans.com/569476853

Agenda

Installation status
  • Schedule
    • Transition from vac/mech to girder hook-ups planned to begin April 5 (5 weeks from today) - maybe 1 or 2 weeks earlier
    • 4 weeks (Apr 5 - Apr 30) are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
  • Beam line layout
    • Preliminary ME songsheet released, up to date as of Feb 23 on the upgrade home page => CEBAF Injector Upgrade
    • 3D CAD model exists if you want to see something not there now
    • Cables: Like before trays (above & on girder) + 3 cable bundle drops (near Y, Laser, Chopper)
DC/Magnet Jobs
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • Done (JM) Complete magnet table I circulated
  • (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • (LL/JM) Second QW measurement, what's the scope here?
  • (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker
CIS Magnet Jobs