Difference between revisions of "March 1, 2021 - DC/Magnet Installation Kickoff"

From Ciswikidb
Jump to navigation Jump to search
Line 6: Line 6:
 
; Installation status
 
; Installation status
 
* Schedule
 
* Schedule
**Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''')
+
**Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''') - maybe 1 or 2 weeks earlier
**We may be ready early by 1 or 2 weeks (no sooner than mid-March)
+
**'''4 weeks (Apr 5 - Apr 30)''' are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
**Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30) w/ HCO/System readiness for everything up to FC#2
 
  
 
*Preliminary Songsheet
 
*Preliminary Songsheet

Revision as of 14:51, 1 March 2021

Meeting Info =

We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion. https://bluejeans.com/569476853

Agenda

Installation status
  • Schedule
    • Transition from vac/mech to girder hook-ups planned to begin April 5 (5 weeks from today) - maybe 1 or 2 weeks earlier
    • 4 weeks (Apr 5 - Apr 30) are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
    • There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable trays (above & on girder) + 3 cable bundle drops (Y, Laser, Chopper)
DC/Magnet Jobs
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • Done (JM) Complete magnet table I circulated
  • (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • (LL/JM) Second QW measurement, what's the scope here?
  • (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker
CIS Magnet Jobs
Plans