March 1, 2021 - DC/Magnet Installation Kickoff

From Ciswikidb
Revision as of 14:53, 1 March 2021 by Grames (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Meeting Info =

We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion. https://bluejeans.com/569476853

Agenda

Installation status
  • Schedule
    • Transition from vac/mech to girder hook-ups planned to begin April 5 (5 weeks from today) - maybe 1 or 2 weeks earlier
    • 4 weeks (Apr 5 - Apr 30) are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
  • Beam line layout
    • Preliminary ME songsheet released, up to date as of Feb 23 on the upgrade home page => CEBAF Injector Upgrade
    • 3D CAD model exists if you want to see something not there now
    • Cables: Like before trays (above & on girder) + 3 cable bundle drops (near Y, Laser, Chopper)
DC/Magnet Jobs
Software Jobs
  • CED
  • Apps
  • Screens
  • What else for software?
Other magnet jobs
  • Done (JM) Complete magnet table I circulated
  • (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
  • (RS/GC) FG solenoid special hysteresis for Gary
  • (RS/MJ) Magnet info for Inj Steer spin calculations
  • (JM/JG) Decision on spare DR fabrication and alignment
  • (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
  • (LL/JM) Second QW measurement, what's the scope here?
  • (JM) When is the rotating coil stand ready?
  • (JM/LL) Reconciling MHD discrepancy
  • (LL) Report on QW
  • (LL) Report on HD
  • (LL) Report on PSS kicker
CIS Magnet Jobs
Plans