March 13, 2017 - 4-Laser/LLRF Installation/Commissioning

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Let's meet Monday March 13th at 11am in the MCC conference room to organize 4-LLRF installation and commissioning. Please come prepared to speak to relevant items below, and/or invite those whom should attend. We'll end the meeting with a ~firm plan that Steve can post to the SAD calendar.

Topics

  1. Plan for 4-LLRF installation
  2. Software controls and screen readiness
  3. FSD implementation and testing
  4. First connection to lasers, manual testing 249/499
  5. Remote HLLAP control of laser frequency
  6. Repair bunch length
  7. Schedule for beam operations
  8. Beam tests: chopper, bunch length, energy spread
  9. Dry run for Fall 4-beam ops
  10. Running during the summer
  11. Installation of final system
  12. Any other topic you'd like to discuss

Summary

4-LLRF Installation
  • Tomasz' readiness/plans presentation media:4Laser_LLRF_March_ready.ppt
  • Estimate is one week to install 4-LLRF system beginning start of SAD (nominally March 23)
  • FSD interface monitors 35/70 MHz; thresholds set in EPICS, Rama working w/ Brad/PSS for FSD node
  • Existing 3-LLRF hardware remains as-is, new 4-LLRF installed near chopper/buncher
  • 4-LLRF application recycles existing EPICS channel names, Rama/Scott will meet before SAD to clarify 3-LLRF vs. 4-LLRF code
  • Once 4-LLRF is up/running and tested OK will coordinate a) Michele's HLAPP test, b) connecting laser ON again
  • Bench test isolation between RF channels >45 dB
  • Tomasz needs to know how precisely power levels should be set for 10 dBm
4-Beam Testing
  • 4-Beam setup of injector to FC2 is vehicle to test system
  • Reza would like spectrum analyzer measurement of existing 3-LLRF vs. new 4-LLRF documented
  • Curt/Reza will continue troubleshooting bunch length system in preparation of beam setup
  • Arne would like a dwell run of ~shifts to demonstrate stability
  • Ops will plan to generally support DAY's to FC2 (and look for a Swing/Owl crew for stability test)