(Created page with "===Topics=== ;200kV Gun status update as of monday, march 11 *fasteners: ordered and due march 6th. '''received and in my cubicle.''' *.015" wire: '''received and handed over...")
 
(7 intermediate revisions by the same user not shown)
Line 1: Line 1:
===Topics===
 
 
;200kV Gun
 
;200kV Gun
 
status update as of monday, march 11
 
status update as of monday, march 11
Line 5: Line 4:
 
*fasteners: ordered and due march 6th. '''received and in my cubicle.'''
 
*fasteners: ordered and due march 6th. '''received and in my cubicle.'''
 
*.015" wire: '''received and handed over.'''
 
*.015" wire: '''received and handed over.'''
*sapphire roller: ordered and due april 12th. '''we have two plus, two rollers supposedly shipped friday.'''
+
*sapphire roller: ordered and due april 12th. '''we have 2 in 1137, plus 2 rollers supposedly shipped friday.'''
*alumina centering ring: ordered and due april 12th. '''we have one in 1137'''
+
*alumina centering ring: ordered and due april 12th. '''we have 1 in 1137'''
*roller pin: machine shop working, requested due date of march 15th?
+
*roller pin: machine shop working, requested due date of march 15th? '''we have 3 in 1137'''
*roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th.
+
*roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th. '''we have 3 in 1137'''
 
* key: '''received and handed over.'''
 
* key: '''received and handed over.'''
 
* aft end: machine shop working with requested due date of march 15th? '''shop says on schedule.'''
 
* aft end: machine shop working with requested due date of march 15th? '''shop says on schedule.'''
 
* ring holder: '''received and handed over.'''
 
* ring holder: '''received and handed over.'''
*[https://logbooks.jlab.org/entry/3661138 Status of small shed cathode electrode]
+
* black insulator on 10" flange '''welded, leak checked, new flange w/ fiducials, worth a survey before mounting electrode?'''
 +
*[https://logbooks.jlab.org/entry/3661138 Status of small shed cathode electrode] '''polished, degassed?'''
 +
 
 +
;Solenoid Update
 +
* Send out for bid early April
 +
* 8 keV solenoids (4 beam line, 2 chopper cavities, 2 chopping chamber)
 +
* Y MeV solenoids
 +
 
 +
;[https://wiki.jlab.org/ciswiki/index.php/200kV_Wien_Filter Wien Filter Update]
 +
*Gabriel status update
  
 
;Spring SAD (April 15 - June 10)
 
;Spring SAD (April 15 - June 10)
 
*List of info I e-mailed to Chris Gould [[media:190228_SA_request.xlsx]]
 
*List of info I e-mailed to Chris Gould [[media:190228_SA_request.xlsx]]
 
*Danny's dwg for survey measurements [[media:190306_S&A CHECKLIST.pdf]]
 
*Danny's dwg for survey measurements [[media:190306_S&A CHECKLIST.pdf]]
 
;Wien Filter
 
*[https://wiki.jlab.org/ciswiki/index.php/200kV_Wien_Filter Link to the Wien filter upgrade page]
 
*Gabriel status update
 
*Wien spin calculation examples for 100kV, 200kV, 350kV, 5MeV, 6.3MeV [[media:190307_SpinCalculator.xlsx]]
 
  
 
;Latest Layouts
 
;Latest Layouts

Revision as of 11:54, 13 March 2019

200kV Gun

status update as of monday, march 11

  • fasteners: ordered and due march 6th. received and in my cubicle.
  • .015" wire: received and handed over.
  • sapphire roller: ordered and due april 12th. we have 2 in 1137, plus 2 rollers supposedly shipped friday.
  • alumina centering ring: ordered and due april 12th. we have 1 in 1137
  • roller pin: machine shop working, requested due date of march 15th? we have 3 in 1137
  • roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th. we have 3 in 1137
  • key: received and handed over.
  • aft end: machine shop working with requested due date of march 15th? shop says on schedule.
  • ring holder: received and handed over.
  • black insulator on 10" flange welded, leak checked, new flange w/ fiducials, worth a survey before mounting electrode?
  • Status of small shed cathode electrode polished, degassed?
Solenoid Update
  • Send out for bid early April
  • 8 keV solenoids (4 beam line, 2 chopper cavities, 2 chopping chamber)
  • Y MeV solenoids
Wien Filter Update
  • Gabriel status update
Spring SAD (April 15 - June 10)
Latest Layouts