* Planning for May
 
* Planning for May
  
=== Eliminating Gun Switch software Gun3 ===
+
=== Eliminating Gun Switch Software ===
 
 
  
 
===Spellman HVPS update===
 
===Spellman HVPS update===

Revision as of 12:28, 30 March 2017

New action items

Electrode/insulator design/fabrication

  • Gabriel assessed fields to vacuum chamber, modified shed radius
  • S&A insulator measurements
  • ME design for shop ... goal was end of March !!!
  • Then ... vacuum fire electrode 900C, barrel polish, assemble to insulator
  • Status of parts

Vacuum chamber/considerations

  • Retain leak valve, add right angle valve through first bake, at least
  • Retain electrical isolation and NEG activation at 100C
  • Pick up ceramics, blow out NEG

Gun2 NEG Tube

  • BPM discussion w/ Musson occurred on Monday, considerations:
    • Antenna : stripline or wire (mini or weld)
    • Position and orientation of antenna v. can for transmission line, length of antenna v. energy
    • NEG coat surfaces of pipe, not can? TBD
    • Re-use Gun3 NEG solenoid
  • Met in tunnel to develop first pass ME design Logbook pic/layout of the existing Gun2 NEG

Gun3 Removal

  • Matt check with Willeke next week for Gun3
  • Marcy submitted ATLIS task for the job
  • Remove Gun3 table, rebuild 8" chamber w/ extractor, RGA, GP-100 on 80/20 stand
  • Recoup Gun3 MFH solenoid
  • Planning for May

Eliminating Gun Switch Software

Spellman HVPS update

  • Mike Johnson has been working on Laser Frequency Divider
  • Time to get him started on Spellman at UITF?

Radmon update