===This Last Week-ish===
+
===Last Week-ish===
 
:'''Bubble Run'''
 
:'''Bubble Run'''
 
::Added new harp w/ temporary controls
 
::Added new harp w/ temporary controls
Line 6: Line 6:
 
::Added x-ray card to locate beam position
 
::Added x-ray card to locate beam position
 
:'''Upgrade Preparations'''
 
:'''Upgrade Preparations'''
::Tested HVPS to 300kV in SF6 tanks at 15psi, and greater
+
::[https://logbooks.jlab.org/entry/3574117 Tested HVPS to 300kV in SF6 tank] at 15psi
 
::Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA
 
::Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA
 
::DecaRad installation below outrigger laser table started, heads/cables ready to dress
 
::DecaRad installation below outrigger laser table started, heads/cables ready to dress
::S&A begin 200kV electrode measurements 5/11 (per last week's plan)
 
::PSS dipole measurements vs. expected gun voltage
 
  
===Next Week and Beyond===
+
===Today, Next Week and Beyond===
 
:Bubble will continue to run until next Friday @ 8am
 
:Bubble will continue to run until next Friday @ 8am
 +
:S&A begin 200kV electrode measurements 5/11 (per last week's plan)
 
:Met w/ Jerry to review PSS integration plans [[media:SAD18_PSS_180511.xlsx]]
 
:Met w/ Jerry to review PSS integration plans [[media:SAD18_PSS_180511.xlsx]]
:Upgrade Week 1 [[media:SAD_180510.docx]]
+
::PSS dipole measurements vs. expected gun voltage
 +
:Upgrade Week #1 (May 21-25) [[media:SAD_180510.docx]]

Latest revision as of 10:51, 11 May 2018

Last Week-ish

Bubble Run
Added new harp w/ temporary controls
Added ceramic break to radiator (shield aimed downstream), in series w/ FCUP
Added Gumby (10 sec) laser shutter, tested w/ beam and remote enable/disable
Added x-ray card to locate beam position
Upgrade Preparations
Tested HVPS to 300kV in SF6 tank at 15psi
Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA
DecaRad installation below outrigger laser table started, heads/cables ready to dress

Today, Next Week and Beyond

Bubble will continue to run until next Friday @ 8am
S&A begin 200kV electrode measurements 5/11 (per last week's plan)
Met w/ Jerry to review PSS integration plans media:SAD18_PSS_180511.xlsx
PSS dipole measurements vs. expected gun voltage
Upgrade Week #1 (May 21-25) media:SAD_180510.docx