May 25, 2017 - 200kV gun upgrade meeting
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
200kV Gun
- Task and Timeline Gantt chart => media:170421_CHG.pdf
325kV Gun .... WHAT ?!?!?
- media:170519_325kV_simulations.pdf => Did we talk about this last week?
Gun2 NEG Tube
- Final NEG tube design => media:NEGTUBE_MAY03.pdf
- Ordered (6) 4.5" rotatable, 2-1/2" bore => (2) in hand, (4) on back order
- Ordered 6" to 4-1/2" reducers =>
- (3) FH sent to MMF => One will be read for NEG tube by next Friday 5/26, others week after
- a) check/replace coil leads w/ 240C insulator as needed, some have old shrink wrap
- b) hi pot each coil
- c) measure each coil using HMIN/HMAX -2.5A/+2.5A
- d) Bz v. z at r=0 ALL (and r=2,4,6 mm for ONE)
- e) Bz v. I at r=0,z=0 ALL
- BPM process : Fabricate, Clean, Leak Test, Optical Align, Electrical Acceptance and/or Gabou Line, Install
- Pete Francis performing optical/electrical acceptance testing...
- M20 #1 (Musson tested) - > First M20 with no serial number optically looks bad and did not pass acceptance test.
- M20 #2 (Musson tested) -> Second M20 with serial no. #PM20-127 looks ok...... but probably could use an Optical Alignment
- M20 #3 (Greg Marble spare) -> Third M20 tested great
- M20 #4 (Greg Marble spare) -> Fourth M20 test occurred during electrical interference, re-test on Monday
- What next?
- Send to shop for modification (327755) => Request June 9
- M20 Old Assembly Modification media:0990.pdf
- M20 New Assembly Can media:0991.pdf
- M20 New Assembly 6.00 x 4.500 reducer flangemedia:0.992.pdf
- Leak check
- Repeat optical/electrical acceptance
- NEG coat
- Gabou measurement
- Install
Gun3 Removal and Diagnostics Chamber Installation
- May 8-12 => Remove and replace Gun3 ATLIS task
- Rebake week of May 30th
Eliminating Gun Switch Software
- April 28 => Remove gun switch software ATLIS task
- Software removed and interlocks tested ELOG entry
- Yet to do a) remove VBV3I02 from special interlock and b) swap PLC for relays