May 26, 2017 - 200kV gun upgrade meeting
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Summer 2017 SAD Update
200kV Gun
- Task and Timeline Gantt chart => media:170421_CHG.pdf
- Simulation of the effect of the mesh and the perforated plate media:170525_Mesh.pdf
NEG Tube
- We are making 4 BPM's
- Shop has materials now and machining (#327755)
- ...then Phil will pick up for weld, 400C bake, leak check, clean, NEG coat
- ...then Pete will perform optical/electrical checks
- ...then John will perform Gabou map
- Final NEG tube design => media:NEGTUBE_MAY03.pdf
- M20 Old Assembly Modification media:0990.pdf
- M20 New Assembly Can media:0991.pdf
- M20 New Assembly 6.00 x 4.500 reducer flangemedia:0.992.pdf
Diagnostics Chamber Installation
- Second bake and activate week of May 30th => Remove and replace Gun3 ATLIS task
- Remove VBV3I02 from special interlock and swap PLC for relays