ME - First installation

  • remove ~4' pipe in straight passthrough
  • add reducer + ceramic break + bubble radiator
  • add MIT bates magnet + Mott detector on the support table
  • realistic time frame for DAQ

ME - Second installation

  • Replace MIT magnet with Lakshmi's magnet
  • Replace Mott detector with Eric's detector

Updates & Discussion