Meeting 2/3/22 - COMTRA

From Ciswikidb
Revision as of 16:09, 2 February 2022 by Grames (talk | contribs)
Jump to navigation Jump to search
  • First installation
    • remove ~4' pipe in straight passthrough
    • add reducer + ceramic break + bubble radiator
    • add MIT bates magnet + Mott detector on the support table
    • realistic time frame for DAQ
  • Second installation
    • Replace MIT magnet with Lakshmi's magnet
    • Replace Mott detector with Eric's detector

Updates & Discussion