Difference between revisions of "Meeting 3/31/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "== Agenda == ; Eric's plan at IJCLab for crystals ; DAQ status ; Magnet status ; UITF plan * April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV v...")
 
 
(6 intermediate revisions by the same user not shown)
Line 2: Line 2:
  
 
; Eric's plan at IJCLab for crystals
 
; Eric's plan at IJCLab for crystals
 +
* Hall A detectors NaI(Tl?) [[media:220331_HallA_NaI2.jpg]]
 +
* IJCLab xstal - winner!
 +
* Saint Gobain xstal - long lead (backups?)
 +
* Alpha spectra xstal - inclusions
 +
* Berkeley Nucleonics - no reply
  
 
; DAQ status
 
; DAQ status
  
 
; Magnet status
 
; Magnet status
 +
* Steel inventory [[media:220324_Steel.jpg]]
 +
* Steel report [[media:Compton_East Carolina Metal treatment metallurgy_3_24_2022.pdf]]
 +
* Sandesh preliminary [[media:UPDATE 1 -COMPTON POLARIZED TARGET MAXWELL Field analysis 032522.pptx]]
  
 
; UITF plan
 
; UITF plan

Latest revision as of 08:59, 31 March 2022

Agenda

Eric's plan at IJCLab for crystals
  • Hall A detectors NaI(Tl?) media:220331_HallA_NaI2.jpg
  • IJCLab xstal - winner!
  • Saint Gobain xstal - long lead (backups?)
  • Alpha spectra xstal - inclusions
  • Berkeley Nucleonics - no reply
DAQ status
Magnet status
UITF plan
  • April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work,
  • May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
  • June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
  • July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
  • Aug - install Compton in MeV section, run keV beam as needed
  • Sep/Oct - calibrate Compton, two separate ~week long runs