Difference between revisions of "Meeting 8/4/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by the same user not shown)
Line 17: Line 17:
  
 
===Detector===
 
===Detector===
* Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]]
+
* Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[File:IMG_20220804_082153706.jpg|thumb]]
* Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]]
+
* Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[File:IMG_20220804_082037794.jpg|thumb]]
 
* Boxes - '''(2) shipped DHL, due 8/9'''
 
* Boxes - '''(2) shipped DHL, due 8/9'''
* BGO - (2) on-hand
+
* BGO - (2) on-hand [[File:IMG_20220804_084436318.jpg|thumb]]
* PMT - on-hand
+
* PMT - on-hand [[File:IMG_20220804_081738760.jpg|thumb]]
 
* Bases - '''due 9/15'''
 
* Bases - '''due 9/15'''
  
 
===Layout===
 
===Layout===
 
* Beamline
 
* Beamline
** Radiator - (1) on-hand, '''(1) need for BNL'''
+
** Radiator - (1) on-hand, '''(1) need for BNL''' [[File:IMG_20220804_084829378.jpg|thumb]]
 
** ?? zero-length reducer 4.5 to 2.75  
 
** ?? zero-length reducer 4.5 to 2.75  
 
** ?? Spool 4.25 lg  [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
 
** ?? Spool 4.25 lg  [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
Line 34: Line 34:
 
** BNL Stand - agreed w/ Cliff, will work up the order
 
** BNL Stand - agreed w/ Cliff, will work up the order
 
* Lead
 
* Lead
** UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8
+
** UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[File:IMG_20220804_084121573.jpg|thumb]]
  
 
===Geant4 Model===
 
===Geant4 Model===

Latest revision as of 08:56, 4 August 2022

Thursday's @ 9am EDT by Zoom

Schedule

  • Installation jobs may begin as early as next week and must be completed by end of Sep
  • Run is planned for October exact dates TBD
  • We will share the run period with another MeV energy experiment

Magnet

DAQ

  • PMT-5R ItoV - on-hand
  • Cables - pull from control room to cave

Detector

Layout

Geant4 Model

Documentation