- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
Schedule
- Installation jobs may begin as early as next week and must be completed by end of Sep
- Run is planned for October exact dates TBD
- We will share the run period with another MeV energy experiment
Magnet
- Kepco PS - due 8/12 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
- Magnet - due 7/15 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
DAQ
- PMT-5R ItoV - on-hand
- Cables - pull from control room to cave
Detector
- Collimator - (2) on-hand media:JL0015777_Cu_collimator.pdf
- Absorbers - (6) on-hand media:Absorber - 240 D 001 14_V4.pdf
- Boxes - (2) shipped DHL, due 8/9
- BGO - (2) on-hand
- PMT - on-hand
- Bases - due 9/15
Layout
- Beamline
- Radiator - (1) on-hand, (1) need for BNL
- ?? zero-length reducer 4.5 to 2.75
- ?? Spool 4.25 lg media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf
- Stands
- UITF PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
- * Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
- BNL Stand - agreed w/ Cliff, will work up the order
- Lead
- UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8
Geant4 Model
Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint