===7/28/22 Update===
+
===Schedule===
;Analyzing Magnet
+
* Installation jobs may begin as early as next week and must be completed by end of Sep
* Kepco PS ('''due week of Aug 8th''') => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
+
* Run is planned for October exact dates TBD
* Magnet '''(request 7/15)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
+
* We will share the run period with another MeV energy experiment
  
;DAQ & RACK
+
===Magnet===
* PMT-5R ItoV amplifier (due TBD)
+
* Kepco PS - '''due 8/12''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
* To-do => final cable, connector, rack layout
+
* Magnet - '''due 7/15''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
  
;Detector
+
===DAQ ===
* BGO crystals - '''Arrived at JLab, stored in cabinet'''
+
* PMT-5R ItoV - on-hand
* PMTs '''(arrived 8/2)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
+
* Cables - '''pull from control room to cave'''
* PMT bases '''(due 8/1-9/15)'''
 
* Detector boxes '''(shipped, DHL estimate 8/9)'''
 
  
;ME
+
===Detector===
* UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
+
* Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[File:IMG_20220804_082153706.jpg|thumb]]
** zero-length reducer 4.5 to 2.75. Do you want us to procure or do you want to search for one?
+
* Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[File:IMG_20220804_082037794.jpg|thumb]]
** Spool 4.25 lg. Do you want us to fab a new spool or do you want to search/ cut/reweld a spool? [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
+
* Boxes - '''(2) shipped DHL, due 8/9'''
* UITF Lead
+
* BGO - (2) on-hand [[File:IMG_20220804_084436318.jpg|thumb]]
:: 2 X 4 X 4 – Need 11
+
* PMT - on-hand [[File:IMG_20220804_081738760.jpg|thumb]]
:: 2 X 4 X 6 – Need 2
+
* Bases - '''due 9/15'''
:: 2 X 4 X 8 – Need 99
 
* BNL Stand - agreed w/ Cliff, will work up the order
 
* Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
* Radiator '''(1) completed, (1) needed'''
 
* Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => '''(2) completed'''
 
* Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => Machine Shop request in [https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm;jsessionid=72888DCB6ACFE194CC116F841A221DB1.cfusion?request_id=331095&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11 Shop job]
 
  
;Geant4 Model
+
===Layout===
 +
* Beamline
 +
** Radiator - (1) on-hand, '''(1) need for BNL''' [[File:IMG_20220804_084829378.jpg|thumb]]
 +
** ?? zero-length reducer 4.5 to 2.75
 +
** ?? Spool 4.25 lg  [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
 +
* Stands
 +
** UITF PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
 +
** * Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 +
** BNL Stand - agreed w/ Cliff, will work up the order
 +
* Lead
 +
** UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[File:IMG_20220804_084121573.jpg|thumb]]
 +
 
 +
===Geant4 Model===
 
*
 
*
  
;Documentation
+
===Documentation===
 
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
 
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
 
* Manual - Sharepoint
 
* Manual - Sharepoint

Latest revision as of 08:56, 4 August 2022

Thursday's @ 9am EDT by Zoom

Schedule

  • Installation jobs may begin as early as next week and must be completed by end of Sep
  • Run is planned for October exact dates TBD
  • We will share the run period with another MeV energy experiment

Magnet

DAQ

  • PMT-5R ItoV - on-hand
  • Cables - pull from control room to cave

Detector

Layout

Geant4 Model

Documentation