Meeting 9/21/22 - COMTRA

From Ciswikidb
Revision as of 20:55, 21 September 2022 by Grames (talk | contribs)
Jump to navigation Jump to search
Thursday's @ 9am EDT by Zoom

Readiness Updates

  • ME/Layout
    • Mike/Eric completed quick reference => ME can use to populate songsheet
    • Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)
  • Experiment components
    • collimator installed and aligned =>
    • magnet measurement, status for install
    • detector assembly, fiducialization => walkthrough completed wit
  • I&C jobs
    • Remote motion control for aperture (otherwise do by hand w/ access) => done
    • Attach current monitors to aperture and dump => done
    • Plumb LCW for current monitor and dump => done 0.75 gpm, SSG update FSD text
    • Pull 6 fibers from DAQ to mezzanine => not yet
    • Align x-ray camera for x-ray card after collimator => ?
    • Insertable 1/2-waveplate
    • pull Heliax to gun rack => done, cable #10
  • DAQ/Controls
    • Helicity generator
    • High Voltage
    • EFADC/DAQ
    • Kepco PS
  • Experiment sequence
    • Pre-Beam - complete HCO, magnet ready, assembly detector ready, fiducial them, mock-up install ?, remove temporarily
    • Commission - setup beam to FCUP, APERTURE, DUMP and use x-ray card to define orbit to collimator
    • Experiment - install/align magnet/detector (w/ attenuators?), deliver x-rays, optimize DAQ, measure asymmetry vs. XYZ and with Wien


Older Links