Meeting 9/8/22 - COMTRA

From Ciswikidb
Revision as of 20:16, 7 September 2022 by Grames (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Thursday's @ 9am EDT by Zoom

New UITFList entries

Readiness Updates

  • Vacuum component layout/shielding
    • Updated ME model w/ dimensions (collimator length, insertable aperture, stand points)
    • Vacuum assembly later today (add aperture, spool, reducer, ceramic, dump)
    • Schedule S&A as-found
  • Detector table/shielding
    • Waiting on table top, then rails/posts assembly
    • Drawings for lead hut assembly
  • Detector status
    • Detector Triax (4) and SHV (2) => cables pulled and hanging near dump
    • DAQ status/readiness
    • Assemble BGO/PMT into detector chassis
  • Magnet
    • Magnet PS cables => pulled to power load on wall
    • Rack/magnet ground cable => bounded to braid near dump
  • Current monitoring
    • Faraday cups current monitor => Ganged with FCUP
    • A5 current monitor => 7mm aperture, requires I&C controls (Windham next week)
    • A6 current monitor => Radiator
  • Position/Size
    • Harp installed upstream of dump
    • BPM installed upstream of dump
    • Beam line viewer => Matt repaired, requires camera alignment
    • X-ray viewer => Joe relocated to look at detector hut, requires X-ray card
  • SImulations
    • compute integrated asymmetry
    • use slurm to run jobs on farm
    • simulate 5 configurations

DAQ

Beamline

Magnet

Detector

Geant4 Model

Action Items

Documentation