= Commissioning =
 
= Commissioning =
 
; Schedule Update
 
; Schedule Update
 +
* Dec 2-16 : injector commissioning (parasitic opportunity)
 +
* Dec 7 : mott commissioning 0400 - 2000 (will ask to break into 4+12)
 +
* Jan (2-10) - Feb 6 : 1-pass commissioning (parasitic opportunity)
 +
* Feb 6 - Feb 27 : SAD (vent for dump, fix mirror, ideally new targets)
 +
* Feb 28 - June 6 : ACC-II (long commissioning run)
 +
 
; Target ladder
 
; Target ladder
 
; Reduced rep rate beam
 
; Reduced rep rate beam

Revision as of 09:38, 20 November 2013

Mott Team Meeting

We will meet next on Wednesday November 20th at 3pm EST locally in TL-1227 (1st floor conference room near CIS offices) or call in by ReadyTalk details below.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 3441852, followed by “#”

Commissioning

Schedule Update
  • Dec 2-16 : injector commissioning (parasitic opportunity)
  • Dec 7 : mott commissioning 0400 - 2000 (will ask to break into 4+12)
  • Jan (2-10) - Feb 6 : 1-pass commissioning (parasitic opportunity)
  • Feb 6 - Feb 27 : SAD (vent for dump, fix mirror, ideally new targets)
  • Feb 28 - June 6 : ACC-II (long commissioning run)
Target ladder
Reduced rep rate beam
DAQ status

New Dump

Status
Simulations