Mott Team Meeting

We will meet next on Wednesday November 20th at 3pm EST locally in TL-1227 (1st floor conference room near CIS offices) or call in by ReadyTalk details below.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 3441852, followed by “#”

Commissioning

Schedule Update
  • Dec 2 - Dec 16 : injector commissioning (parasitic opportunity)
  • Dec 7 : mott commissioning 0400 - 2000 (will ask to break into 4+12)
  • Jan (2-10) - Feb 6 : 1-pass commissioning (parasitic opportunity)
  • Feb 6 - Feb 27 : SAD (vent for dump, fix mirror, ideally new targets)
  • Feb 28 - June 6 : ACC-II (long commissioning run)
Target ladder
Reduced rep rate beam
DAQ status

New Dump

Status
  • Given present schedule want parts in-hand by Jan 17th (week to clean & prep)
  • Be plate - Materion sending quote, will turn into PR
  • Cu end cap - RFQ's sent to 3 local vendors today
Simulations