October 12, 2016 - 4-Laser/LLRF Monthly Status Meeting

From Ciswikidb
Revision as of 09:55, 12 October 2016 by Grames (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Agenda

1. Proposed Installation Schedule Winter SAD Schedule

  • There are ~3 weeks in January for this job: Jan 3 (return to work) to Jan 27 (CEBAF restoration)
  • Week 1 (Jan 4-11) Install LLRF, connect lasers when makes sense, test ability to move between 250/500, verify proper power levels to lasers, and check reproducibility.
  • Week 2 (Jan 12-18) Injector lock-ups and make e-beam, test against rf sensitive elements like bunchers, chopper, and unit when 2K is restored.
  • Week 3 (Jan 19-25) Evaluate and make sure front end is performing well, finalize/rectify outstanding issues, worst case backout.

2. Tomasz - LLRF update

3. Software Request to switch laser/LLRF between 250/499 MHz media:161012_4Laser4LLRF.docx