October 15, 2020 - Weekly ME meeting

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Info =

We will meet Thursday @ 10am EDT via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 909497334#
Passcode : 2864   (anybody can then start the meeting)

Meeting October 15

From Joe, here is the latest on the AIPINJ magnets (priorities #5, #4, #2, #3, #1)
  • FX & FY solenoids (Everson Tesla): Mike QC’d the last shipment of magnets and spare coils. They passed and we have accepted all 10 solenoids and 4 coils. All ETI measurement data is within the +/-5 G-cm requirement. Will send out to Jay and Lakshmi. Invoices have been approved and paid. The tooling was also shipped and can be stored with us if needed.
  • DR dipole (Milhous): The 2nd half of the first article is being wound. ETA is next week. Will look to put on measurement stand ASAP.
  • HD (Technicoil): Stainless bobbins completed. Starting winding. On schedule to be finished by 10/23.
  • QW (Technicoil); No updates; will follow-up with Technicoil.
  • Wien Dipole (Carlos): Wien cores delivered to MMF shop. Mike will start the coil fit-up process with coils and vacuum chamber next week (10/19-10/23). Mike performs final assembly and measurements first two weeks of Nov. (11/3-11/13).
PSS kicker
  • Lakshmi completing analysis (due latest Monday) on PSS kicker using 3 types of conductor (reason for add'l work is long lead time availability of Plan A wire)
  • Jerry providing input on PSS power supply
  • We'll evaluate options and schedule soon, then pick a direction

Meeting October 8

Component status
Wien quads => due 11/20
Wien quads fixture parts => incomplete
Wien quad crosses => due 10/30
Wien quad tapped flanges => due 10/14
Wien filter fixtures => due 8/21 (????)
Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing
Wien viewer extension shafts => We have those
Prebuncher cavity => on track for 11/1
Prebuncher amp => due 10/29
Viewer plates and top hats => completed
Chromox viewers => due 10/8
Parts to rebuild remaining viewers => from Tony?
A1/A2 fixture parts => due 10/30
A1/A2 cube mods => completed
A1/A2 spools => due 9/25 (delivered?)
MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18
Pedestals => due 11/10
Gamma Ion Pumps => due 11/2
Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
Remaining Jobs
0      Layout & Points for Gun table + 2I pedestal => top priority
1	Viewer assembly fixture => Marcy has one, would like if a lighter color
2	Will NEG fit 25 l/sec IP on Y => Marcy will check, ask for ENG help if needed
3	Viewer garage dwg => Shaun gave to Danny
4	wien filter electrodes 1 piece => Keith getting ready to place order
5	A1/A2 assembly drawing => Shaun gave to Danny
6	MQW cross assembly/mounting parts => See Danny on Monday
7	PSS kicker magnet => Lakshmi will seutp meeting w/ Jerry/Joe is PLan A OK?
8	finish pre-buncher fab/weld => JOe to check
9	Wien filter girder assembly dwg => Gary updated.....give to Danny?
10	Aperture girder assembly dwg => Gary updated....give to Danny?
11	laser table/encl  => down the road
12	Installation drawings => Shaun still working on this...
13	MHD + MQW protective clamp shells => down the road
14	DR 15 deg dipole shim => Joe!!!
15	DR 15 deg dipole (backup) => FY21 budget updated