Difference between revisions of "October 8, 2020 - Weekly ME meeting"
Jump to navigation
Jump to search
(3 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
== Meeting October 8 == | == Meeting October 8 == | ||
− | ; | + | ; Component status |
− | + | Wien quads => due 11/20 | |
− | + | Wien quads fixture parts => incomplete | |
− | + | Wien quad crosses => due 10/30 | |
− | + | Wien quad tapped flanges => due 10/14 | |
− | + | Wien filter fixtures => due 8/21 (????) | |
− | + | Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing | |
− | + | Wien viewer extension shafts => We have those | |
− | ; | + | Prebuncher cavity => on track for 11/1 |
− | 1 Viewer assembly fixture | + | Prebuncher amp => due 10/29 |
− | 2 Will NEG fit 25 l/sec IP on Y | + | |
− | 3 Viewer garage dwg | + | Viewer plates and top hats => completed |
− | 4 wien filter electrodes 1 piece | + | Chromox viewers => due 10/8 |
− | 5 A1/A2 assembly drawing | + | Parts to rebuild remaining viewers => from Tony? |
− | 6 MQW cross assembly/mounting parts | + | |
− | 7 PSS kicker magnet | + | A1/A2 fixture parts => due 10/30 |
− | 8 finish pre-buncher fab/weld | + | A1/A2 cube mods => completed |
− | 9 Wien filter girder assembly | + | A1/A2 spools => due 9/25 (delivered?) |
− | 10 Aperture girder assembly | + | MHD coils => due 10/23 |
− | 11 laser table/encl | + | |
− | 12 Installation drawings | + | Girders => signed 9/22, due 10/23.....now 11/18 |
− | 13 MHD protective clamp shell | + | Pedestals => due 11/10 |
− | 14 DR 15 deg dipole shim | + | |
− | 15 DR 15 deg dipole (backup) | + | Gamma Ion Pumps => due 11/2 |
+ | Lesker flanges => due 10/16 | ||
+ | |||
+ | 15 deg DR magnet => due 7/10 :( | ||
+ | |||
+ | ;Remaining Jobs | ||
+ | 0 Layout & Points for Gun table + 2I pedestal | ||
+ | 1 Viewer assembly fixture => Marcy, do you really need this, or skip? | ||
+ | 2 Will NEG fit 25 l/sec IP on Y => Marcy, do you need any help? | ||
+ | 3 Viewer garage dwg => Shaun? | ||
+ | 4 wien filter electrodes 1 piece => Place order? | ||
+ | 5 A1/A2 assembly drawing => Shaun? | ||
+ | 6 MQW cross assembly/mounting parts => Not ordered yet | ||
+ | 7 PSS kicker magnet => Lakshmi? | ||
+ | 8 finish pre-buncher fab/weld => on track | ||
+ | 9 Wien filter girder assembly dwg => Shaun? | ||
+ | 10 Aperture girder assembly dwg => Shaun? | ||
+ | 11 laser table/encl | ||
+ | 12 Installation drawings => Shaun? | ||
+ | 13 MHD protective clamp shell => required for a bake | ||
+ | 14 DR 15 deg dipole shim => required for evaluation ? | ||
+ | 15 DR 15 deg dipole (backup) => let's evaluate the first vendor |
Latest revision as of 11:16, 8 October 2020
Meeting Info
We will meet Thursday @ 10am EDT via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 909497334#
Meeting October 8
- Component status
Wien quads => due 11/20 Wien quads fixture parts => incomplete Wien quad crosses => due 10/30 Wien quad tapped flanges => due 10/14 Wien filter fixtures => due 8/21 (????) Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing Wien viewer extension shafts => We have those
Prebuncher cavity => on track for 11/1 Prebuncher amp => due 10/29
Viewer plates and top hats => completed Chromox viewers => due 10/8 Parts to rebuild remaining viewers => from Tony?
A1/A2 fixture parts => due 10/30 A1/A2 cube mods => completed A1/A2 spools => due 9/25 (delivered?) MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18 Pedestals => due 11/10
Gamma Ion Pumps => due 11/2 Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
- Remaining Jobs
0 Layout & Points for Gun table + 2I pedestal 1 Viewer assembly fixture => Marcy, do you really need this, or skip? 2 Will NEG fit 25 l/sec IP on Y => Marcy, do you need any help? 3 Viewer garage dwg => Shaun? 4 wien filter electrodes 1 piece => Place order? 5 A1/A2 assembly drawing => Shaun? 6 MQW cross assembly/mounting parts => Not ordered yet 7 PSS kicker magnet => Lakshmi? 8 finish pre-buncher fab/weld => on track 9 Wien filter girder assembly dwg => Shaun? 10 Aperture girder assembly dwg => Shaun? 11 laser table/encl 12 Installation drawings => Shaun? 13 MHD protective clamp shell => required for a bake 14 DR 15 deg dipole shim => required for evaluation ? 15 DR 15 deg dipole (backup) => let's evaluate the first vendor