(Created page with "== Meeting Info == We will meet Thursday @ 10am EDT <u>'''via BlueJeans'''</u> Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (f...")
 
Line 7: Line 7:
 
== Meeting October 8 ==
 
== Meeting October 8 ==
  
; ME status from Last Week
+
; Phase 1 jobs done last week
 
+
MQW order placed.
'''Phase 1 - Done'''
+
special wien filter cross order placed.
* MQW order placed.
+
A1/A2 fixture order placed.
* special wien filter cross order placed.
+
girders order placed.
* A1/A2 fixture order placed.
+
viewer plate and top hats in, i think.
* girders order placed.
+
pedestals order placed.
* viewer plate and top hats in, i think.
+
A1/A2 cube mods finished from machine shop.
* pedestals order placed.
 
* A1/A2 cube mods finished from machine shop.
 
  
 
;Priority Remaining Phase 1 Jobs
 
;Priority Remaining Phase 1 Jobs

Revision as of 17:41, 7 October 2020

Meeting Info

We will meet Thursday @ 10am EDT via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 909497334#

Meeting October 8

Phase 1 jobs done last week
MQW order placed.
special wien filter cross order placed.
A1/A2 fixture order placed.
girders order placed.
viewer plate and top hats in, i think.
pedestals order placed.
A1/A2 cube mods finished from machine shop.
Priority Remaining Phase 1 Jobs
1	Viewer assembly fixture
2	Will NEG fit 25 l/sec IP on Y
3	Viewer garage dwg
4	wien filter electrodes 1 piece
5	A1/A2 assembly drawing
6	MQW cross assembly/mounting parts
7	PSS kicker magnet
8	finish pre-buncher fab/weld
9	Wien filter girder assembly
10	Aperture girder assembly
11	laser table/encl
12	Installation drawings (all)
13	MHD protective clamp shell
14	DR 15 deg dipole shim
15	DR 15 deg dipole (backup)