Difference between revisions of "October 8, 2020 - Weekly ME meeting"
Jump to navigation
Jump to search
(Created page with "== Meeting Info == We will meet Thursday @ 10am EDT <u>'''via BlueJeans'''</u> Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (f...") |
|||
Line 7: | Line 7: | ||
== Meeting October 8 == | == Meeting October 8 == | ||
− | ; | + | ; Phase 1 jobs done last week |
− | + | MQW order placed. | |
− | + | special wien filter cross order placed. | |
− | + | A1/A2 fixture order placed. | |
− | + | girders order placed. | |
− | + | viewer plate and top hats in, i think. | |
− | + | pedestals order placed. | |
− | + | A1/A2 cube mods finished from machine shop. | |
− | |||
− | |||
;Priority Remaining Phase 1 Jobs | ;Priority Remaining Phase 1 Jobs |
Revision as of 17:41, 7 October 2020
Meeting Info
We will meet Thursday @ 10am EDT via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 909497334#
Meeting October 8
- Phase 1 jobs done last week
MQW order placed. special wien filter cross order placed. A1/A2 fixture order placed. girders order placed. viewer plate and top hats in, i think. pedestals order placed. A1/A2 cube mods finished from machine shop.
- Priority Remaining Phase 1 Jobs
1 Viewer assembly fixture 2 Will NEG fit 25 l/sec IP on Y 3 Viewer garage dwg 4 wien filter electrodes 1 piece 5 A1/A2 assembly drawing 6 MQW cross assembly/mounting parts 7 PSS kicker magnet 8 finish pre-buncher fab/weld 9 Wien filter girder assembly 10 Aperture girder assembly 11 laser table/encl 12 Installation drawings (all) 13 MHD protective clamp shell 14 DR 15 deg dipole shim 15 DR 15 deg dipole (backup)