Line 8: | Line 8: | ||
; Phase 1 jobs done last week | ; Phase 1 jobs done last week | ||
− | + | Wien quads => due 11/20 | |
− | + | Wien quads fixture parts => incomplete | |
− | A1/A2 fixture | + | Wien quad crosses => due 10/30 |
− | + | Wien quad tapped flanges => due 10/14 | |
− | + | Wien filter fixtures => due 8/21 (????) | |
− | + | ||
− | + | A1/A2 fixture parts => due 10/30 | |
+ | A1/A2 cube mods => completed | ||
+ | A1/A2 spools => due 9/25 (delivered?) | ||
+ | MHD coils => due 10/23 | ||
+ | |||
+ | Girders => signed 9/22, due 10/23.....now 11/18 | ||
+ | Pedestals => due 11/2 | ||
+ | |||
+ | Prebuncher cavity => on track for 11/1 | ||
+ | Prebuncher amp => due 10/29 | ||
+ | |||
+ | Viewer plates and top hats => completed | ||
+ | Chromox viewers => due 10/8 | ||
+ | |||
+ | Gamma Ion Pumps => due 11/2 | ||
+ | |||
+ | Lesker flanges => due 10/16 | ||
+ | |||
+ | 15 deg DR magnet => due 7/10 :( | ||
;Priority Remaining Phase 1 Jobs | ;Priority Remaining Phase 1 Jobs | ||
Line 29: | Line 47: | ||
11 laser table/encl | 11 laser table/encl | ||
12 Installation drawings (all) | 12 Installation drawings (all) | ||
− | 13 MHD protective clamp shell | + | 13 MHD protective clamp shell => required for a bake |
− | 14 DR 15 deg dipole shim | + | 14 DR 15 deg dipole shim => required for evaluation ? |
− | 15 DR 15 deg dipole (backup) | + | 15 DR 15 deg dipole (backup) => let's evaluate the first vendor |
Revision as of 08:15, 8 October 2020
Meeting Info
We will meet Thursday @ 10am EDT via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 909497334#
Meeting October 8
- Phase 1 jobs done last week
Wien quads => due 11/20 Wien quads fixture parts => incomplete Wien quad crosses => due 10/30 Wien quad tapped flanges => due 10/14 Wien filter fixtures => due 8/21 (????)
A1/A2 fixture parts => due 10/30 A1/A2 cube mods => completed A1/A2 spools => due 9/25 (delivered?) MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18 Pedestals => due 11/2
Prebuncher cavity => on track for 11/1 Prebuncher amp => due 10/29
Viewer plates and top hats => completed Chromox viewers => due 10/8
Gamma Ion Pumps => due 11/2
Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
- Priority Remaining Phase 1 Jobs
1 Viewer assembly fixture 2 Will NEG fit 25 l/sec IP on Y 3 Viewer garage dwg 4 wien filter electrodes 1 piece 5 A1/A2 assembly drawing 6 MQW cross assembly/mounting parts 7 PSS kicker magnet 8 finish pre-buncher fab/weld 9 Wien filter girder assembly 10 Aperture girder assembly 11 laser table/encl 12 Installation drawings (all) 13 MHD protective clamp shell => required for a bake 14 DR 15 deg dipole shim => required for evaluation ? 15 DR 15 deg dipole (backup) => let's evaluate the first vendor