; Phase 1 jobs done last week
 
; Phase 1 jobs done last week
  MQW order placed.
+
  Wien quads => due 11/20
  special wien filter cross order placed.
+
Wien quads fixture parts => incomplete
  A1/A2 fixture order placed.
+
Wien quad crosses => due 10/30
  girders order placed.
+
Wien quad tapped flanges => due 10/14
  viewer plate and top hats in, i think.
+
  Wien filter fixtures => due 8/21 (????)
  pedestals order placed.
+
 
  A1/A2 cube mods finished from machine shop.
+
  A1/A2 fixture parts => due 10/30
 +
A1/A2 cube mods => completed
 +
A1/A2 spools => due 9/25 (delivered?)
 +
MHD coils => due 10/23
 +
 
 +
Girders => signed 9/22, due 10/23.....now 11/18
 +
Pedestals => due 11/2
 +
 
 +
  Prebuncher cavity => on track for 11/1
 +
Prebuncher amp => due 10/29
 +
 
 +
  Viewer plates and top hats => completed
 +
Chromox viewers => due 10/8
 +
 
 +
Gamma Ion Pumps => due 11/2
 +
 
 +
  Lesker flanges => due 10/16
 +
 
 +
  15 deg DR magnet => due 7/10 :(
  
 
;Priority Remaining Phase 1 Jobs
 
;Priority Remaining Phase 1 Jobs
Line 29: Line 47:
 
  11 laser table/encl
 
  11 laser table/encl
 
  12 Installation drawings (all)
 
  12 Installation drawings (all)
  13 MHD protective clamp shell
+
  13 MHD protective clamp shell => required for a bake
  14 DR 15 deg dipole shim
+
  14 DR 15 deg dipole shim => required for evaluation ?
  15 DR 15 deg dipole (backup)
+
  15 DR 15 deg dipole (backup) => let's evaluate the first vendor

Revision as of 08:15, 8 October 2020

Meeting Info

We will meet Thursday @ 10am EDT via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 909497334#

Meeting October 8

Phase 1 jobs done last week
Wien quads => due 11/20
Wien quads fixture parts => incomplete
Wien quad crosses => due 10/30
Wien quad tapped flanges => due 10/14
Wien filter fixtures => due 8/21 (????)
A1/A2 fixture parts => due 10/30
A1/A2 cube mods => completed
A1/A2 spools => due 9/25 (delivered?)
MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18
Pedestals => due 11/2
Prebuncher cavity => on track for 11/1
Prebuncher amp => due 10/29
Viewer plates and top hats => completed
Chromox viewers => due 10/8
Gamma Ion Pumps => due 11/2
Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
Priority Remaining Phase 1 Jobs
1	Viewer assembly fixture
2	Will NEG fit 25 l/sec IP on Y
3	Viewer garage dwg
4	wien filter electrodes 1 piece
5	A1/A2 assembly drawing
6	MQW cross assembly/mounting parts
7	PSS kicker magnet
8	finish pre-buncher fab/weld
9	Wien filter girder assembly
10	Aperture girder assembly
11	laser table/encl
12	Installation drawings (all)
13	MHD protective clamp shell => required for a bake
14	DR 15 deg dipole shim => required for evaluation ?
15	DR 15 deg dipole (backup) => let's evaluate the first vendor