Difference between revisions of "October 8, 2020 - Weekly ME meeting"

From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by the same user not shown)
Line 7: Line 7:
 
== Meeting October 8 ==
 
== Meeting October 8 ==
  
; Phase 1 jobs done last week
+
; Component status
 
  Wien quads => due 11/20
 
  Wien quads => due 11/20
 
  Wien quads fixture parts => incomplete
 
  Wien quads fixture parts => incomplete
Line 13: Line 13:
 
  Wien quad tapped flanges => due 10/14
 
  Wien quad tapped flanges => due 10/14
 
  Wien filter fixtures => due 8/21 (????)
 
  Wien filter fixtures => due 8/21 (????)
 +
Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing
 +
Wien viewer extension shafts => We have those
 +
 +
Prebuncher cavity => on track for 11/1
 +
Prebuncher amp => due 10/29
 +
 +
Viewer plates and top hats => completed
 +
Chromox viewers => due 10/8
 +
Parts to rebuild remaining viewers => from Tony?
  
 
  A1/A2 fixture parts => due 10/30
 
  A1/A2 fixture parts => due 10/30
Line 20: Line 29:
  
 
  Girders => signed 9/22, due 10/23.....now 11/18
 
  Girders => signed 9/22, due 10/23.....now 11/18
  Pedestals => due 11/2
+
  Pedestals => due 11/10
 
 
Prebuncher cavity => on track for 11/1
 
Prebuncher amp => due 10/29
 
 
 
Viewer plates and top hats => completed
 
Chromox viewers => due 10/8
 
  
 
  Gamma Ion Pumps => due 11/2
 
  Gamma Ion Pumps => due 11/2
 
 
  Lesker flanges => due 10/16
 
  Lesker flanges => due 10/16
  
 
  15 deg DR magnet => due 7/10 :(
 
  15 deg DR magnet => due 7/10 :(
  
;Priority Remaining Phase 1 Jobs
+
;Remaining Jobs
  1 Viewer assembly fixture
+
0      Layout & Points for Gun table + 2I pedestal
  2 Will NEG fit 25 l/sec IP on Y
+
  1 Viewer assembly fixture => Marcy, do you really need this, or skip?
  3 Viewer garage dwg
+
  2 Will NEG fit 25 l/sec IP on Y => Marcy, do you need any help?
  4 wien filter electrodes 1 piece
+
  3 Viewer garage dwg => Shaun?
  5 A1/A2 assembly drawing
+
  4 wien filter electrodes 1 piece => Place order?
  6 MQW cross assembly/mounting parts
+
  5 A1/A2 assembly drawing => Shaun?
  7 PSS kicker magnet
+
  6 MQW cross assembly/mounting parts => Not ordered yet
  8 finish pre-buncher fab/weld
+
  7 PSS kicker magnet => Lakshmi?
  9 Wien filter girder assembly
+
  8 finish pre-buncher fab/weld => on track
  10 Aperture girder assembly
+
  9 Wien filter girder assembly dwg => Shaun?
  11 laser table/encl
+
  10 Aperture girder assembly dwg => Shaun?
  12 Installation drawings (all)
+
  11 laser table/encl  
 +
  12 Installation drawings => Shaun?
 
  13 MHD protective clamp shell => required for a bake
 
  13 MHD protective clamp shell => required for a bake
 
  14 DR 15 deg dipole shim => required for evaluation ?
 
  14 DR 15 deg dipole shim => required for evaluation ?
 
  15 DR 15 deg dipole (backup) => let's evaluate the first vendor
 
  15 DR 15 deg dipole (backup) => let's evaluate the first vendor

Latest revision as of 11:16, 8 October 2020

Meeting Info

We will meet Thursday @ 10am EDT via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/909497334
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 909497334#

Meeting October 8

Component status
Wien quads => due 11/20
Wien quads fixture parts => incomplete
Wien quad crosses => due 10/30
Wien quad tapped flanges => due 10/14
Wien filter fixtures => due 8/21 (????)
Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing
Wien viewer extension shafts => We have those
Prebuncher cavity => on track for 11/1
Prebuncher amp => due 10/29
Viewer plates and top hats => completed
Chromox viewers => due 10/8
Parts to rebuild remaining viewers => from Tony?
A1/A2 fixture parts => due 10/30
A1/A2 cube mods => completed
A1/A2 spools => due 9/25 (delivered?)
MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18
Pedestals => due 11/10
Gamma Ion Pumps => due 11/2
Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
Remaining Jobs
0      Layout & Points for Gun table + 2I pedestal
1	Viewer assembly fixture => Marcy, do you really need this, or skip?
2	Will NEG fit 25 l/sec IP on Y => Marcy, do you need any help?
3	Viewer garage dwg => Shaun?
4	wien filter electrodes 1 piece => Place order?
5	A1/A2 assembly drawing => Shaun?
6	MQW cross assembly/mounting parts => Not ordered yet
7	PSS kicker magnet => Lakshmi?
8	finish pre-buncher fab/weld => on track
9	Wien filter girder assembly dwg => Shaun?
10	Aperture girder assembly dwg => Shaun?
11	laser table/encl 
12	Installation drawings => Shaun?
13	MHD protective clamp shell => required for a bake
14	DR 15 deg dipole shim => required for evaluation ?
15	DR 15 deg dipole (backup) => let's evaluate the first vendor