Meeting October 8

Component status
Wien quads => due 11/20
Wien quads fixture parts => incomplete
Wien quad crosses => due 10/30
Wien quad tapped flanges => due 10/14
Wien filter fixtures => due 8/21 (????)
Wien filter rebuild => Carlos' 8-week rebuild => both due by 11/30 for HV testing
Wien viewer extension shafts => We have those
Prebuncher cavity => on track for 11/1
Prebuncher amp => due 10/29
Viewer plates and top hats => completed
Chromox viewers => due 10/8
Parts to rebuild remaining viewers => from Tony?
A1/A2 fixture parts => due 10/30
A1/A2 cube mods => completed
A1/A2 spools => due 9/25 (delivered?)
MHD coils => due 10/23
Girders => signed 9/22, due 10/23.....now 11/18
Pedestals => due 11/10
Gamma Ion Pumps => due 11/2
Lesker flanges => due 10/16
15 deg DR magnet => due 7/10 :(
Remaining Jobs
0      Layout & Points for Gun table + 2I pedestal
1	Viewer assembly fixture => Marcy, do you really need this, or skip?
2	Will NEG fit 25 l/sec IP on Y => Marcy, do you need any help?
3	Viewer garage dwg => Shaun?
4	wien filter electrodes 1 piece => Place order?
5	A1/A2 assembly drawing => Shaun?
6	MQW cross assembly/mounting parts => Not ordered yet
7	PSS kicker magnet => Lakshmi?
8	finish pre-buncher fab/weld => on track
9	Wien filter girder assembly dwg => Shaun?
10	Aperture girder assembly dwg => Shaun?
11	laser table/encl 
12	Installation drawings => Shaun?
13	MHD protective clamp shell => required for a bake
14	DR 15 deg dipole shim => required for evaluation ?
15	DR 15 deg dipole (backup) => let's evaluate the first vendor